Bond Progress

Bond Projects - Status as of May 8, 2024

Projects

Construction Bid

Construction Start

Expense as of 5/8/2024

Estimated Construction End

Estimated Final Cost

West Field HS (New Build)

$154,431,924

2/1/2022

$122,550,443

August 2024

$154,431,924

Mountain View JHS (New Build)

$62,688,570

4/22/2022

$55,765,214

August 2024

$62,688,570

Haven Bay Elem. (New Build)

$42,741,300

3/1/2023

$24,246,207

August 2024

$42,741,300

Roosevelt Elem. (Replacement)

$46,393,324

12/20/2023

$2,605,300

August 2025

$46,393,324

Total

$306,255,118

 

$205,167,164

 

$306,255,118

Progress Report October 2023

Progress of Mountain view bond as of october 2023

Progress of Mountain view bond as of october 2023

Progress of Mountain view bond as of october 2023

Progress Report 7/7/2023

The work continues on our three new schools in Western Weber County. West Field High School, Mountain View Jr. High, and the yet to be named new elementary, are all slated to open for the 2024-25 school year. 

Congrats to Mike Russell on being named the athletic director at West Field.  Mike comes to us from Syracuse High.  Angie Bodily from Roy High School has also been selected as the new head secretary.

Progress for three new schools in Western Weber County

Progress for three new schools in Western Weber County

Progress for three new schools in Western Weber County

Progress Report 5/7/2022

Report of bond progress as of may 7th 2022

Report of bond progress as of may 7th 2022

Report of bond progress as of may 7th 2022